Background

Located at the Northwest corner of SE 276th Street and state route 169, directly behind (West of) the Les Schwab Tire Center, the Summit Park & Ballfields site was purchased in 2006 from the Tahoma School District for development as a Community Park with an emphasis on athletic fields.

In 2010 the City Council adopted a master plan for the then 22.75-acre site, and selected a phasing plan that would result in the park being developed in three (3) separate construction phases over several years. Due to a lack of funding, the project was put on hold.

In 2013, the Tahoma School District approached the City about jointly developing the property as part of their proposed new high school project on the adjoining 35-acres that the District was looking to purchase from King County.

In 2014, with the District’s purchase of the 35-acres from the County nearing completion, the City agreed to sell 8.18 acres of the Summit Park property to the Tahoma School District at no cost to provide the District with needed land for bus and visitor parking, and to build intersection improvements at SE 271st St. and State Route 169, and build an access road leading to the east side of the new Tahoma High School.

In exchange for the property, the City will receive free use of the parking lot (during non-school hours) and unlimited use of the access road to get to the future park site, rather than enter and exit the park from SE 276th St.

Beginning in 2015, the City began working on a revised master plan for the remaining 14.57 acres of the Community Park site that would serve the community, the City’s Parks & Recreation Department programs and Tahoma High School athletic teams.

Over a period of several months staff vetted the revised plan at no less than nine (9) public events to solicit public input on the design elements of the draft plan.  In April 2016, and again in February 2017, the project was included in two separate bond measures. 

After the last bond measure didn’t pass in 2017, the City Council directed the Parks & Recreation Commission to come back to them with alternative options to consider for developing the Park.

Three (3) separate joint meetings were held between the City Council and the Parks & Recreation Commission to discuss various park projects, available funding sources, partnerships, timing, etc. and on June 14, 2017 the City Council unanimously approved a range of funding sources for the Summit Park project, and directed staff to proceed with finalizing the master plan.

The master plan has been submitted to the Bonneville Power Administration (BPA) for review as the site is encumbered with a 375-foot wide easement that bisects at a diagonal through the property.  All construction within the easement needs to conform to BPA standards to be permitted. Until BPA completes its design review, the master plan remains in draft form.

Once the revised master plan is approved by BPA, the master plan will be reviewed by the Parks & Recreation Commission and then forwarded to the City Council for adoption. Both of these meetings will provide an opportunity for public comment on the draft master plan.

Next Steps

It is expected that adoption of the master plan, and design development work will continue into the fall of 2017. If there are no unforeseen delays, the project is expected to go to bid in early 2018.  Construction would start in late winter or early spring of 2018 and be completed in late fall of 2018.

For more information, contact Greg Brown, Parks and Recreation Director at 425-432-9953, or at greg.brown@maplevalleywa.gov

Summit Park Master Plan 6-29-2017 - 070717

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer